Santushti Ongoing Project in Ranchi

Overview

"Santushti" Project Crowned Residential Project of the Year (East) - "Santushti" bagged the Residential Project of the Year (East) award at the 2nd BERG Real Estate Awards. The award was presented to Mr Bijay Kumar Agarwal, Managing Director, Pranami Estates Pvt Ltd at the Gala Awards Night on July 24 evening in Singapore. Conceptualised and hosted by Singapore-based Business Excellence & Research Group (BERG), the awards also recognised the contribution of many developers, architects and interior designers from India.


At Santushti you are offered a successful lifestyle equipped with every comfort that you need to make living a real pleasure.

Santushti provides easy access and parking for residents. It is located in the heart of Ranchi and is in close proximity to University, Stadium, Market Complexes and Entertainment Zones, Bus Stand & Railway Station within 1 Km distance.

Features

Special Features :

  • Exclusive modern Facade
  • Grand entrance with landscaped driveway
  • 6 exclusive stainless steel Automatic lifts of which 3 are large enough for stretchers
  • Integrated Security surveillance system of common areas
  • Landscaped garden with Children's play area
  • Air-condition Community hall, Gymnasium and club house
  • Efficient fire-fighting equipment and fire escape stairways
  • Sufficient Car parking space
  • 3 Deep tube wells for adequate water supply
  • DG back up with extra cost for uninterrupted power supply
  • Rain water harvesting

Specification

Main Structure

Foundation & Structure

RCC framed structure designed as per the seismic requirement as stipulated by BIS codes.


Walls

As per the requirement of the architect.   

Staircase/common area


Flooring

Living room/Dining room/Other bedrooms
Vitrified Tiles of superior quality.

Master bedrooms
Vitrified tiles/ laminated wooden textured board of superior quality

Utility room
Vitrified I non skid Tiles of superior quality.

Kitchen


Flooring

Superior quality non skid Tiles.

Counter

Superior quality  granite slab

Dado

Superior quality glazed tiles.

Water Connection

Provision for water lines with good quality UPVC pipe with joints and valves of reputed make.

Fitting/fixtures

SS sink and fixtures of reputed make.


Toilets


Flooring

Vitrified / non skid Tiles.

Basin

Basin of superior quality.

Wall finish

Vitrified / glazed ceramic Tiles up to Door height

Water connection

Provision for water lines with good quality UPVC pipe joints and valves of reputed make

Sanitaryware

Superior quality sanitaryware and fittings of reputed make.

CP-fitting/fixtures/accessories

reputed make.

Wall/ceiling finish

Plaster of paris.

Doors

Superior quality Flush Doors.

External glazing

Windows - 3 track sliding Aluminium windows


Electricals

Fixture/fittings of reputed make. DG power back up with extra cost. 
Wiring
Concealed ISI marked fire resistant copper wiring in PVC conduit pipe.

Communication/Security

Telephone
Prewired upto one no telephone point in individual apartment as per architect's specifications.


Cable/DTH

Prewired upto livingn room and bed rooms for cable/DTH television in individual apartment.


Security system
Security surveillance system of common areas.

Fire fighting system
As per design of the fire consultants and safety rules and regulations.


Water supply

Deep tube well
3 deep tube wells for water supply

 

Santushti

Church Road, Ranchi

 

Santushti : Construction Progress

27
Jul
2017
Tower C: Slab shuttering, Rod binding & column shuttering ongoing, Plumbing 2nd Floor ongoing, etc.
24
Jul
2017
Tower A: 10th Floor tiles work ongoing, etc.
24
Jul
2017
Tower B: OHT shuttering ongoing, Tiles work in 4th, 5th & 7th floor, Outer Plaster ongoing
22
May
2017
Tower A: 10th & 11th Floor Tiles and Granite Work Ongoing, 11th Floor POP ongoing, Texture work ongoing
22
May
2017
Tower B: 10th Floor Brick Work Complete, 9th Floor Plaster Work Ongoing, 8th Floor POP Ongoing
22
May
2017
Tower C: 6th Floor Shuttering Ongoing, 3rd & 4th Floor Brick Work Ongoing, 1st & 2nd Floor Plumbing Work Ongoing
24
Apr
2017
Tower A: 10th floor tiles work ongoing, Waterproofing in terrace floor ongoing, etc
24
Apr
2017
Tower B: 9th Floor brick work ongoing, 8th floor plaster complete, POP 7th floor complete
24
Apr
2017
Tower C: 3rd floor brick work ongoing, ground floor plaster ongoing.
23
Mar
2017
Tower A: Brick work in Terrace Floor, Tiles work in 7th, 8th & 9th floor, Plumbing work 11th floor, etc
23
Mar
2017
Tower B: 11th Floor shuttering completed, 9th floor brick work ongoing, 7th Plaster work ongoing, etc
23
Mar
2017
Tower C: 5th Floor Shuttering & Casting ongoing
11
Jan
2017
Block A: OH Water Tank Shuttering, 11th Floor Brick Work, 8th Floor POP, 6th Floor Tiles, & 7th Floor Water Proofing Ongoing
11
Jan
2017
Block B: 7th Floor Plaster, 9th Floor Shuttering, 2nd Floor Tiles & 6th Floor Water Proofing Ongoing
11
Jan
2017
Block C: 2nd Floor Brick Work, 4th Floor Shuttering & Ground Floor Plaster Ongoing
15
Dec
2016
Block A: OH Tank Rod Binding, Parapet Wall Casting, 11th Floor Brick Work, 7th Floor POP, 10 Floor Plaster, 4th Floor Tiles & 7th Floor Water-proofing Ongoing
15
Dec
2016
Block B: 7th Floor Plaster & 5th Floor POP Ongoing
15
Dec
2016
Block C: 1st Floor Brick Work & 3rd Floor Half Part Shuttering Ongoing
18
Nov
2016
Tower A: Mumty Level Casting Ongoing, Parapet Wall Shuttering Ongoing, 11th Floor Brick Work Ongoing, 6th Floor POP Ongoing, 8th & 9th Floor Plaster Ongoing, 3rd Floor Tiles Ongoing
18
Nov
2016
Tower B: 6th Floor Plaster Work Ongoing, 2nd & 3rd Floor Waterproofing Ongoing
18
Nov
2016
Tower C: 3rd Floor Half Part Casting Ongoing & Half Part Shuttering Ongoing
04
Oct
2016
Tower C: Ground Floor Roof Casting Completed. First Floor Roof Shuttering Ongoing.
26
Sep
2016
Tower B: 8th Floor Column Shuttering & Steel Work Ongoing. 6th Floor Plaster Completed. 1st Floor POP Completed. 1st Floor Plumbing Ongoing.
26
Sep
2016
Tower C: Ground Floor Roof Half Casting Completed & Rest Shuttering & Steel Work Ongoing
26
Sep
2016
Main Gate
10
Sep
2016
Tower - A: 10th Floor Roof Casting completed. 11th Floor Roof Shuttering ongoing. 2nd Floor Tiles work ongoing. 7th Floor Brick & Plaster work ongoing. 9th Floor Brick work ongoing.
10
Sep
2016
Tower - B: 8th Floor Column Casting Ongoing
10
Sep
2016
Tower - C: Ground Floor Roof Shuttering ongoing
20
Aug
2016
Tower A: 9th Floor Roof Casting Completed. 10th Floor Roof Shuttering ongoing
20
Aug
2016
Tower B: 7th Floor Roof Casting Completed
20
Aug
2016
Tower C: Ground Floor Roof Shuttering ongoing
20
Aug
2016
Entrance Gate: Shuttering ongoing
09
Aug
2016
Tower A: 9th Floor Roof Casting
09
Aug
2016
Tower B: 7th Floor Roof Casting
09
Aug
2016
Tower C: Ground Floor Roof Shuttering ongoing
26
Jul
2016
Tower A: 9th Floor Roof Shuttering ongoing
26
Jul
2016
Tower B
08
Jul
2016
Tower B: 7th Floor Roof Shuttering
08
Jul
2016
Tower A: 8th Floor Roof Casting
11
May
2016
Tower A: 7th Floor Roof Casting, Tower B: 6th Floor Roof Centering, Tower C: Extended Basement Centering Completed
11
Apr
2016
Tower A: 6th Floor Roof Casting, Tower B: 5th Floor Roof Shuttering Ongoing, Tower C: Extended Basement Retaining Wall Casting
10
Mar
2016
Tower A: 6th Floor Roof Shuttering ongoing
10
Mar
2016
Tower B: 4th Floor Roof Shuttering ongoing
10
Mar
2016
Tower C: Extended Basement Slab Shuttering ongoing
10
Feb
2016
Tower A: 5th Floor Roof Shuttering Ongoing. 2nd Floor Brick Work Ongoing.
10
Feb
2016
Tower B: 3rd Floor Roof Casting Ongoing. 1st Floor Brick Work Ongoing
10
Feb
2016
Tower C: Extended Basement Raft Work Ongoing. RCC Wall Casting Ongoing.
04
Feb
2016
Tower A: 5th Floor Roof Shuttering ongoing
25
Jan
2016
Tower A: 5th Floor 50% Casting completed. Casting preparation for rest 50% is ongoing
25
Jan
2016
Tower B: 3rd Floor Roof Shuttering is ongoing
25
Jan
2016
Tower C: Slab Casting of Ground Floor completed. Excavation of extended basement is ongoing
07
Jan
2016
Project Status: Tower A - 4th Floor Roof Casted, Tower B - 3rd Floor Casting, Tower C - Ground Floor Roof Casting Preparation
08
Dec
2015
Project Status: Tower A- 3rd Floor Roof Casting, Tower B - 2nd Floor Roof Casted, Tower C - Basement Roof Casted (Half)
14
Nov
2015
Project Status: Tower A - 3rd Floor Roof Casting, Tower B - 2nd Floor Roof Casting, Tower C - Basement Roof Casting
28
Oct
2015
Project status as on 28-10-2015
12
Oct
2015
Project status as on 12-10-2015
12
Sep
2015
Project status as on 12-09-2015
20
Aug
2015
Project status as on 20-08-2015
22
Jul
2015
Work Progress till date
04
Jul
2015
Work Progress till date
30
May
2015
Work Progress till date
04
Apr
2015
Work Progress till date
28
Feb
2015
Work Progress till date
18
Dec
2014
BLOCK - A & B
02
Dec
2014
Raft Working & Fire Fighting and Domestic Water Reserve In Progress
14
Nov
2014
Raft Working Progress
11
Jul
2014
PCC Work Started
26
May
2014
Land Soil Cutting started.